| BH Series - | Installation Instructions |
|
|
|
|
| Determine proper
mounting location. Assure a mounting angle greater than 20 degrees unless
'SP' type.
A backing plate is recommended to reinforce the bin wall (usually the same thickness as the bin wall) Install mounting bolts 'B' through holes in mounting channel 'A' () Weld both channel legs to hopper wall or backing plate (skip weld and avoid ends) with low hydrogen rod. Install and thread lockwashers and nuts 'D' tighten securely. Install a safety cable (part number CB 0.00) from the eye of the vibrator to a permanent structure nearby. Following air supply connection, operate vibrator for a short period and retighten all fasteners. |
![]() |
|
|
| Install air control
package ()
Fill the lubricator with SAE 10 or lighter non-detergent oil. Set pressure regulator to 50 p.s.i. Open Valve Adjust the lubricator to approximately 10 drops of oil per minute. Operate vibrator for five minutes Inspect and re-tighten all mounting fasteners and air line connections. Adjust air regulator for the lowest pressure which will give the the desired material flow performance. Not to exceed 60 psi. Periodically fill oil reservoir to assure lubrication for the vibrator. All vibrators must be installed with an inline lubricator, filter and regulator. |
![]() |
NEED
A BH?
< Request a Quote Online for a BH Pneumatic Piston Vibrator >
ALREADY
HAVE A BH?
< Get BH Vibrator
Operation and Maintenance info here >
< Get Pneumatic Piston Vibrator Lubrication Instructions here >